KYOCERA AVX Suzhou: Anticipating Material Shortages Before Line Stoppages with Lean SMT Material Management
Smart Manufacturing in Practice
In SMT manufacturing, placement machines continuously consume electronic components at high speeds. A production line typically consists of multiple machines, feeding areas, and numerous feeder positions. Even a single feeder running out of components can disrupt the production rhythm of the entire line. Particularly in high-mix manufacturing environments with frequent product changeovers, material consumption rates vary according to placement programs, making it difficult to determine the appropriate replenishment time through manual inspections or remaining component quantities alone.
To address material monitoring and shortage warning requirements on SMT production lines, KYOCERA AVX Suzhou partnered with Hegong Software to implement an SMT Production Line Monitoring System (PLMS) based on RockPlus LeanFac, its lean factory management platform. Through integration with ASM SIPLACE placement machines, the system transforms equipment-level material consumption data into actionable information for material replenishment.
Remaining Material Quantity and Remaining Production Time Are Two Different Things
During component placement, consumption rates vary significantly between different electronic components. For example, a remaining quantity of 100 components may provide sufficient preparation time when only one component is required per PCB. However, the same quantity may be depleted much sooner when multiple components are required for each board.
Relying solely on remaining quantities can lead to premature preparation of low-consumption materials or delayed replenishment of high-consumption materials. Personnel responsible for multiple placement machines must also consider the current production cycle time when determining replenishment priorities across different feeder positions.
RockPlus LeanFac retrieves the active Recipe from ASM SIPLACE placement machines, including component placement counts, PCB panel configurations, and production cycle times. By combining these parameters with actual material quantities at each feeder position, the system dynamically estimates how many boards can still be produced and how much production time remains.
For feeder positions with spliced material reels, the system identifies the relationships between consecutive reels and calculates their combined remaining quantities, avoiding unnecessary shortage warnings based solely on the quantity of the currently active reel.
When a production line changes products or downloads a new placement program, the system automatically detects Recipe changes, retrieves the corresponding component consumption parameters, and updates its material consumption forecasts. Shortage warnings therefore remain aligned with the current production task.
Consolidating Material Information from Multiple Placement Machines into a Single Interface
ASM SIPLACE placement machines provide comprehensive production program and material management capabilities. However, shop-floor personnel responsible for multiple production lines and machines need a centralized interface that provides a clear overview of material availability.
In this project, RockPlus LeanFac integrates with SIPLACEPro and SIPLACE SetupCenter to retrieve production line configurations, machine information, production programs, feeder positions, active material reels, and remaining quantities. This creates a dedicated material monitoring application while preserving the existing equipment management processes.
The system establishes hierarchical relationships between production lines, placement machines, feeding areas, feeder positions, and feeders according to the actual production line layout. It also accommodates different feeding area configurations across SIPLACE machine models.
Operators can monitor material availability across multiple production lines or select a specific line and drill down to an individual placement machine or feeding area.
The monitoring interface displays the current production program, material codes, feeder positions, remaining quantities, estimated remaining board counts, and remaining production time. Data is automatically refreshed at configurable intervals, with materials at risk of shortage prioritized in the display.
Personnel can identify materials requiring immediate attention and locate their corresponding feeder positions without checking each machine individually.
Yellow and Red Warnings Help Operators Prioritize Material Replenishment
When multiple feeder positions simultaneously approach material depletion, operators need to know not only which materials are running low but also which require immediate attention and which still allow sufficient preparation time.
RockPlus LeanFac establishes a multidimensional warning mechanism based on remaining production time, estimated remaining board count, and minimum remaining material quantity. Yellow warnings and red alarms distinguish different levels of material shortage risk.
For example, the remaining production time can be configured with a yellow warning threshold of 10 minutes and a red alarm threshold of 5 minutes. When the estimated remaining production time reaches the corresponding threshold, the material record is automatically highlighted in the appropriate color.
For materials that meet the configured alarm conditions, the system can also display prominent pop-up notifications accompanied by repeated audible alerts, reducing the risk of personnel overlooking critical shortage information.
Warning thresholds are configurable rather than fixed. Managers can adjust yellow and red thresholds for all three monitoring indicators, as well as data refresh intervals, according to production cycle times, material delivery distances, reel splicing preparation times, and staffing arrangements.
This approach allows shop-floor personnel to prioritize material preparation and reel splicing according to actual consumption conditions. Replenishment activities can begin before materials are depleted, rather than after a placement machine has stopped due to a material shortage.
Bringing Lean Management to the Shop Floor Without Disrupting Existing Equipment Operations
For SMT production lines already in operation, digital transformation should make effective use of existing equipment data while minimizing disruption to established manufacturing processes.
In this project, RockPlus LeanFac combines equipment data integration with an independent monitoring application. By periodically retrieving production programs and material information from SIPLACE systems, it forecasts material consumption and identifies potential shortages without requiring a separate material loading management process or modifying the original placement machine control logic.
From remaining reel quantities within equipment systems to estimated production time on monitoring dashboards and subsequent material preparation and reel splicing activities, data originally used primarily for equipment operation becomes a practical resource for lean shop-floor management.
For continuously operating SMT production lines, identifying a potential material shortage several minutes in advance gives personnel additional time to prepare the required components.
By transforming material consumption data into clear and actionable warnings, RockPlus LeanFac provides digital support for reducing material-related waiting time, minimizing the risk of unplanned production line stoppages, and maintaining stable production rhythms.